Project Work Plan

1. PRE-DESIGN July 31- Aug 4


    1.1. Detailed Analytic Review WS LIB SITES

    1.2. Detailed Analytic Review All Referenced Similar Sites

    1.3. Detailed Analysis all WSLib materials available by mail or
    electronic media

    1.4. Explore graphic, video & sound enhancement possibilities

    1.5. Meet in Olympia w/ WS Lib personnel



2. DRAFT DESIGN August 7 - 25


    2.1. Prepare detailed work schedule, projected review points, prepare
    network display of development events and activities

    2.2. Receive any additional assets from WSLib

    2.3. Propose selection of audio & visual enhancements, draft selected

    2.4. Draft Basic WSLib Compatible Site Template & appropriate
    variations

    2.5. Draft Navigational scheme

    2.6. Optimize Provided Scenarios for Web Presentations

    2.7. Optimize/Modify/Add Text as required

    2.8. Draft Layout of all pages.

    2.9. Develop intra-site link structure

    2.10 Create review platform; install draft site on NetPaths.net server

    2.11 Modify elements per on-going review with WSLib liaison

    2.12 Be present/available as approriate for repsonse to August 25
    review


3. IMPLEMENT REVIEW DIRECTED MODIFICATION
& FINAL DESIGN – August 28 - September 22


    3.1. Resolve, incorporate site review input

    3.2. Complete user interactivity programming

    3.3. Continue liaison throughout phase 3

    3.4. Process or polish all visual assets

    3.5. Finalize and polish all text assets

    3.6. Install additional links as appropriate


4. Forward files to WSLib 9/22

Available tech support as necessary following deployment.


   

 