Project Work Plan
1. PRE-DESIGN July 31- Aug 4
1.1. Detailed Analytic Review WS LIB SITES
1.2. Detailed Analytic Review All Referenced Similar Sites
1.3. Detailed Analysis all WSLib materials available by mail or
electronic media
1.4. Explore graphic, video & sound enhancement possibilities
1.5. Meet in Olympia w/ WS Lib personnel
2. DRAFT DESIGN August 7 - 25
2.1. Prepare detailed work schedule, projected review points, prepare
network display of development events and activities
2.2. Receive any additional assets from WSLib
2.3. Propose selection of audio & visual enhancements, draft selected
2.4. Draft Basic WSLib Compatible Site Template & appropriate
variations
2.5. Draft Navigational scheme
2.6. Optimize Provided Scenarios for Web Presentations
2.7. Optimize/Modify/Add Text as required
2.8. Draft Layout of all pages.
2.9. Develop intra-site link structure
2.10 Create review platform; install draft site on NetPaths.net server
2.11 Modify elements per on-going review with WSLib liaison
2.12 Be present/available as approriate for repsonse to August 25
review
3. IMPLEMENT REVIEW DIRECTED MODIFICATION
& FINAL DESIGN August 28 - September 22
3.1. Resolve, incorporate site review input
3.2. Complete user interactivity programming
3.3. Continue liaison throughout phase 3
3.4. Process or polish all visual assets
3.5. Finalize and polish all text assets
3.6. Install additional links as appropriate
4. Forward files to WSLib 9/22
Available tech support as necessary following deployment.